Attached ADU
ADUs · Attached

Attached ADU

New living space seamlessly bolted to your existing home — shared wall, separate life, one utility bill.

400–1,200 sq ft
Typical size
6–9 months
On-site build
$150K
Starting at
Inspections + handoff
Closeout
What we build

Attached ADU across Los Angeles, Orange & Ventura Counties.

An attached ADU shares one wall with your main house. It's the right move when your lot is tight, when you want to keep utilities simple, or when architectural integration matters more than full separation.

Because you're leveraging an existing wall, foundation edge, and often utility runs, attached ADUs typically come in 15–25% below the cost of a comparable detached unit. Same 1,200 sq ft state maximum. Same rentable status. Same address if you want one.

Most attached ADUs finish in 6–9 months on site. We build across LA, OC, and Ventura.

Options

Ways homeowners use this addition.

Side attached ADU

Off the side of the house — often replaces an unused side yard with a full 1-bedroom unit.

Rear attached ADU

Extends off the back of the house — preserves the front elevation completely.

Attached studio

Compact 400–500 sq ft unit — cheapest attached configuration.

Attached 1-bedroom

The rental sweet spot — bedroom, full bath, kitchen, living.

Attached 2-bedroom

For multi-generational family or premium long-term rental.

Attached + interior connection

Locking interior door between main house and ADU — flexible for aging parents or teen suite.

All-in scope

What's included in every HomeAdd project.

Architectural design
Integrated design that reads as part of the house.
Structural engineering
Foundation, framing, seismic, and connection to the existing structure.
Title 24 & MEP design
Energy compliance and MEP design.
Local ADU permits
California's 60-day state ADU timeline applies. We file and manage.
Utility connections
Shared or separate — we advise based on your goals.
Foundation & framing
New footings tied to existing structure, matched framing.
Full kitchen & bath
Cabinetry, counters, appliances, fixtures installed.
HVAC
Mini-split system sized for the ADU.
Interior finishes
Flooring, paint, trim, doors, hardware.
Detailed construction proposal
Defined scope with itemized allowances after design.
Dedicated project manager
Weekly updates through handoff.
Project closeout
Final inspections, punch list, and applicable warranty documentation per the signed contract.
Timeline

A realistic schedule, phase by phase.

  1. 1
    Feasibility & design
    4–5 weeks

    Site walk, zoning check, design.

  2. 2
    Construction docs
    4–5 weeks

    Engineering, Title 24, MEP, permit set.

  3. 3
    Plan check & permits
    6–10 weeks

    California's 60-day ADU review clock, corrections, permit.

  4. 4
    Site prep & foundation
    2 weeks

    Foundation, footings tied to existing structure.

  5. 5
    Framing & envelope
    3–5 weeks

    Framing, roofing, windows, matched exterior.

  6. 6
    MEP & insulation
    3–4 weeks

    Rough electrical, plumbing, HVAC, insulation.

  7. 7
    Kitchen, bath, finishes
    4–5 weeks

    Cabinetry, tile, flooring, paint, fixtures.

  8. 8
    Final inspection & handoff
    1 week

    Building final, address (if separate), punch list, warranty.

Investment

What it costs in LA, Orange & Ventura Counties.

Preliminary planning ranges vary by jurisdiction, site conditions, design, utilities, and finish level. A written proposal follows feasibility and design.

Attached studio (400–500 sq ft)
starting at $150K

One-room unit with full kitchen and bath.

Attached 1-bedroom (600–800 sq ft)
starting at $200K

Separated bedroom, full bath, kitchen, living.

Attached 2-bedroom (900–1,200 sq ft)
starting at $285K

Larger family-scale ADU with premium finishes.

Permits & code

Filed, corrected, inspected — by us.

We submit to LADBS, LA County DPW, and every OC and Ventura jurisdiction weekly. You never touch a portal, sit on hold, or drive to a counter.

  • ADU permit (California's 60-day review timeline)
  • Structural plan check
  • Title 24 energy compliance
  • MEP permits
  • Utility separation (as needed)
  • Fire separation between units
  • Address assignment (as configured)
  • Final building inspection & CofO
Reference imagery

What this scope typically looks like.

Representative planning images of the kind of build described above.

Attached ADU integrated with main home
Attached ADU framing
Alternative detached ADU option
Above-garage ADU option
Interior finish detail
FAQ

Answers we give on most first calls.

Still have questions? Call (877) 544-1543 or request a callback — a HomeAdd project advisor will walk your address on Google Earth with you on the phone.

Attached vs detached — which should I build?+

Attached is cheaper (15–25%) and faster. Detached commands slightly higher rent and offers real separation. If your lot supports either, we walk you through the tradeoffs in feasibility.

Do we need a fire wall between the ADU and main house?+

Yes — a one-hour rated wall assembly is standard where the two units meet. We include it in every attached ADU we build.

Can utilities be shared?+

Yes for most systems. Some cities require separate water sub-meters for ADUs. We confirm your city's rule and design accordingly.

Can I add an interior door between the two?+

Absolutely. A locking interior connection is popular for aging-in-place, teen suites, and hybrid live-work setups. Doesn't affect the ADU's rentable status when locked.

Does an attached ADU affect my property tax?+

Yes, but only the added square footage is reassessed at current construction value — not the whole property. In LA that's usually far less than clients expect.

How much rent for an attached ADU?+

Attached ADUs typically rent within 5–10% of comparable detached units. In the SFV, 1-bedrooms rent $2,500–$3,600/month.

Ready to plan your attached adu?

We'll walk your property, pull the zoning, and give you a real budget and timeline — before you spend a dollar on design.