A brand new full or half bath added to your home — designed, permitted, and built end-to-end.

30–90 sq ft
Typical size
6–12 weeks
On-site build
$30K
Starting at
Inspections + handoff
Closeout
What we build

Bathroom Addition across Los Angeles, Orange & Ventura Counties.

Not a remodel — a brand new bathroom where one didn't exist before. Off a primary bedroom, off a guest room, off a home office, or a first-floor half bath for a two-story house that never had one.

The hard part is never the tile — it's the plumbing routing, venting, and permit path. We handle all of it: drain lines, vent stacks, water supply, electrical, and local building department approvals. You pick the tile.

Typical size is 30–90 sq ft. Timeline is 6–12 weeks on site. Fully permitted.

Options

Ways homeowners use this addition.

First-floor powder room

A half bath for older two-story homes that only have baths upstairs — often carved from a hall closet.

New primary ensuite

Add a full ensuite bath to a bedroom that never had one — tub or shower plus vanity and toilet.

Guest bath

A full bath off a guest bedroom or ADU, permitted as a real independent bathroom.

Jack-and-Jill

A shared bath between two kids' bedrooms with two vanities and separate toilet/shower.

Basement bath

New bath in a converted basement — often requires a sewage ejector pump we spec and install.

Pool / cabana bath

A permitted half or 3/4 bath off the yard for pool use — great value for entertaining.

All-in scope

What's included in every HomeAdd project.

Bath design
Layout, fixture selection, tile selection, and lighting plan.
Plumbing engineering
Drain, waste, vent (DWV) routing designed and permitted.
Electrical work
GFCI outlets, exhaust fan on timer, lighting circuit, and heater when included.
Permits, handled
We file and manage every submittal, correction, and inspection with your local building department.
Framing modifications
Wall changes, blocking for grab bars, and any structural work required.
Waterproofing
Full pan liner, membrane, and code-compliant waterproofing under all tile.
Tile & fixtures
Installed by our tile crew — floor, walls, shower niche, and accent.
Vanity & counter
Semi-custom or custom vanity with quartz or stone top and undermount sink.
Toilet, sink, tub / shower
Fixtures installed by qualified trade professionals and inspected as required.
Ventilation
Code-compliant exhaust fan vented to exterior — never into the attic.
Detailed construction proposal
Defined scope with itemized allowances after design.
Project closeout
Final inspections, punch list, and applicable warranty documentation per the signed contract.
Timeline

A realistic schedule, phase by phase.

  1. 1
    Design & feasibility
    2–3 weeks

    Site walk, plumbing route, fixture selection.

  2. 2
    Permit set
    2–3 weeks

    Drawings, MEP, permit package.

  3. 3
    Plan check & permits
    4–8 weeks

    Plan-check submittal, corrections, and permit issuance.

  4. 4
    Demo & rough plumbing
    1 week

    Selective demo, DWV rough, water lines, gas as needed.

  5. 5
    Rough inspections
    1 week

    Plumbing, electrical, mechanical rough inspections.

  6. 6
    Framing patch & waterproofing
    1 week

    Backer board, waterproof membrane, blocking.

  7. 7
    Tile & finishes
    2–3 weeks

    Tile setting, grout, paint, vanity, toilet, mirror.

  8. 8
    Final inspection & handoff
    3–5 days

    Building final, punch list, closeout package.

Investment

What it costs in LA, Orange & Ventura Counties.

Preliminary planning ranges vary by jurisdiction, site conditions, design, utilities, and finish level. A written proposal follows feasibility and design.

Half bath / powder room
starting at $30K

Toilet, sink, small vanity, and mid-range tile in ~30 sq ft.

New full bath (60 sq ft)
starting at $50K

Tub or shower, toilet, vanity, standard tile, exhaust fan.

Spa-quality primary ensuite (90+ sq ft)
starting at $85K

Freestanding tub, oversized shower, double vanity, upgraded tile and fixtures.

Permits & code

Filed, corrected, inspected — by us.

We submit to LADBS, LA County DPW, and every OC and Ventura jurisdiction weekly. You never touch a portal, sit on hold, or drive to a counter.

  • Building permit (as required)
  • Plumbing permit
  • Electrical permit
  • Mechanical / ventilation permit
  • Structural review (for wall changes)
  • Waterproofing inspection
  • Fixture rough-in inspection
  • Final building inspection
Reference imagery

What this scope typically looks like.

Representative planning images of the kind of build described above.

New primary bathroom with freestanding tub
Bath rough framing and plumbing
Home exterior after addition
Adjacent bedroom finish detail
Bathroom tile and vanity detail
FAQ

Answers we give on most first calls.

Still have questions? Call (877) 544-1543 or request a callback — a HomeAdd project advisor will walk your address on Google Earth with you on the phone.

Can any bedroom become an ensuite?+

Almost always yes. Plumbing routing is the constraint — we look at joist direction, existing stacks, and slab-vs-crawlspace access in the design walk. Usually there are two or three viable configurations.

How long is the bathroom out of service?+

For a new bath addition, your existing baths aren't disturbed — only the new space is under construction. If we're re-plumbing existing lines you might have a day or two of coordinated shut-off.

Do I need a permit for a small bath?+

Yes. Any new plumbing fixture triggers permits in LA. We handle it — you should never let a contractor talk you out of pulling permits.

Can we upsize the water heater at the same time?+

Yes, and often you should. We calculate demand from the new fixtures and recommend a tankless upgrade if capacity is tight. Included as a line item so there are no surprises.

Freestanding tub vs built-in?+

Freestanding tubs are stunning but require freestanding-style plumbing and often floor reinforcement. Built-in tubs are cheaper and hide plumbing. We show both options in design.

Can we add heated floors?+

Yes. Electric radiant is easy under tile. We spec it during design and include it as an allowance so you can decide with actual pricing.

Ready to plan your bathroom addition?

We'll walk your property, pull the zoning, and give you a real budget and timeline — before you spend a dollar on design.