Quick answer
State law (Gov. Code §§66310–66342) sets the floor for ADUs in all three cities: 4-foot side and rear setbacks for new detached units, no replacement parking when a garage is converted, a 60-day decision on complete applications, and no impact fees at 750 sq ft or less. On top of that, each city has its own ADU ordinance, and parts of all three sit in the Coastal Zone, where a coastal permit, waiver or exemption may be needed. Redondo Beach issues its own coastal permits; in Torrance and Hermosa Beach the California Coastal Commission does.
Key takeaways
- State ADU law applies in every city; where a local rule conflicts with it, state law controls (Torrance's own FAQ says its 2025 amendments resolve conflicts in favor of state law).
- Torrance and Redondo Beach both offer pre-approved ADU plan programs; Hermosa Beach does not list one.
- Redondo Beach and Hermosa Beach allow ADUs up to 850 sq ft (studio/1-bed) or 1,000 sq ft (2+ bedrooms) under their local standards.
- All three cities bar renting an ADU for less than 30 days.
- Coastal Zone lots need coastal review: Redondo Beach (certified LCP) handles it; Torrance and Hermosa Beach rely on the Coastal Commission.

Whether you are planning a detached ADU, a garage conversion or a junior ADU in Torrance, Redondo Beach or Hermosa Beach, the permit comes from the city, not from Los Angeles County. The rules come in three layers: state ADU law, the city's own ADU ordinance and, for lots in the Coastal Zone, coastal review.
This is general planning information from HomeAdd, not legal advice for your property. City codes, handouts and portals change, and a city's web page can lag behind its code. Confirm current standards with the city that reviews your parcel before you design.
The state rules that apply in all three cities
California's ADU law (Gov. Code §§66310–66342) applies in every city. A city can adopt its own ADU ordinance, but it cannot go below these state standards:
- Side and rear setbacks: no more than 4 feet for a new ADU, and no setback for a conversion of an existing structure or a same-place, same-size rebuild (§66314(d)(7)).
- Parking: at most one space per ADU or per bedroom, whichever is less, and it may be tandem on a driveway (§66314(d)(10)(A)).
- No replacement parking when a garage, carport, covered parking structure or uncovered parking space is demolished or converted for an ADU (§66314(d)(11)).
- Impact fees: none on an ADU of 750 sq ft or less of interior livable space (or a JADU of 500 sq ft or less); larger ADUs are charged proportionately to the main home (§66311.5(c)(1)). More detail is in our ADU impact fees guide.
- Owner occupancy: no owner-occupant requirement may be imposed for ADUs, though a city may require rentals of 30 days or longer (§66315).
- Review clock: the city must decide whether an application is complete within 15 business days, and approve or deny a complete application within 60 days when there is an existing home on the lot (§66317).
The "800 sq ft" ADU
State law also guarantees one detached, new-construction ADU with 4-foot side and rear setbacks; a city may limit it to 800 sq ft of livable space and the state height limits (Gov. Code §66323(a)(2)). The HCD ADU Handbook (March 2026) summarizes the state height limits as 16 feet in general, 18 feet near major transit (plus 2 feet for roof pitch), and up to 25 feet for an attached ADU, or the zone's limit if that is lower. For how setbacks work in practice, see ADU setback requirements in California.
Coastal Zone lots: who issues the coastal permit
ADU law does not override the California Coastal Act, with one exception: a coastal development permit (CDP) for an ADU must be decided within 60 days, and no public hearing is required (Gov. Code §66329(a)). Where a city has no certified Local Coastal Program (LCP), the Coastal Commission approves or denies the ADU CDP within 60 days (§66329(b)(1)).
The Coastal Commission's SB 1077 ADU guidance (July 1, 2026) lists Torrance and Hermosa Beach among the uncertified jurisdictions where the Commission issues CDPs. Redondo Beach is not on that list. Depending on the site, coastal review can end in a CDP, a CDP waiver, or an exemption or categorical exclusion. The Commission's SB 1077 page collects the guidance.
| City | Certified LCP? | Coastal review by |
|---|---|---|
| Torrance | No | California Coastal Commission |
| Redondo Beach | Yes | City of Redondo Beach |
| Hermosa Beach | No | Coastal Commission, South Coast District |
Torrance
ADUs are reviewed by the Community Development Department, through its Planning Division and Building and Safety. The local rules are in Torrance Municipal Code §92.2.10 (ADUs) and §92.2.11 (JADUs).
- 2025 amendments: in October 2025 the City Council adopted ADU ordinance amendments (O-3954) to §92.2.10, which require any conflict with state law to be resolved in favor of state law, according to the city's Planning FAQ. The online code may not yet show those amendments, so confirm current size, height and parking standards with Planning before you design.
- Rentals: an ADU may not be operated as a short-term rental or rented for less than 30 days (TMC §92.2.10(b)(1)).
- Coastal Zone: the Coastal Act applies to ADUs in the Coastal Zone, and a copy of the Coastal Commission approval (CDP, waiver or exemption) must be filed with the building permit application (TMC §92.2.10(c)(3)).
Torrance pre-approved ADU plans
The city's Pre-Approved ADU program offers four one-story plans: a 440 sq ft studio, a 640 sq ft one-bedroom, a two-bedroom of about 750 sq ft and a 798 sq ft two-bedroom. The plans are about 80% complete and pre-reviewed by Building and Safety and Planning. They are purchased from the designers, and they may not fit every site. Our custom ADU vs. pre-approved plans guide covers the trade-offs.
Torrance plan check and permits
Applications go through the city's Online Permit Center portal; the Plan Check page explains the review.
Redondo Beach
The city's ADU page (Community Development, Planning) says a building permit is required and lists a 60-day approval timeframe for complete applications. The rules are in RBMC §10-2.1506 (inland zoning) and §10-5.1506 (coastal zoning), last amended by Ord. 3264 (effective December 8, 2023).
- Size: living area up to 850 sq ft for a studio or one-bedroom ADU, or 1,000 sq ft for more than one bedroom; a JADU up to 500 sq ft (RBMC §10-2.1506).
- Height: the city page lists a 16-foot baseline, 18 feet near transit, and up to 25 feet for attached ADUs. Detached ADUs keep at least 4 feet from the side and rear lot lines.
- Parking: one space per ADU unless an exemption applies; tandem is allowed; no replacement is required when a garage, carport or covered parking is demolished or converted.
- Rentals: terms of 30 or more consecutive days, with no overnight lodging or shorter subleases.
- Owner occupancy: Redondo's code and ADU page still say that for ADUs permitted after January 1, 2025 in single-family zones, either the main home or the ADU must be owner-occupied. Gov. Code §66315 bars owner-occupancy requirements for ADUs. Ask the city how it applies this today.
Redondo Beach pre-approved plans
The city runs an AB 1332 "ADU Master Plan Program", and publishes checklists and a sample approved ADU application.
Redondo Beach coastal review and portals
Redondo Beach has a certified LCP and processes its own coastal review. According to the city's ADU page and RBMC §10-5.2208, it uses Categorical Exclusion Orders where applicable to exempt ADUs, and the City may waive the CDP public hearing for an ADU. Building and planning applications go through the city's iWorQ portals; paper applications are no longer accepted.
Hermosa Beach
The city's ADU page (Community Development, 1315 Valley Dr.) points to Municipal Code Chapter 17.21, most recently amended by Ord. 26-1498 (effective April 23, 2026). The chapter sets up two classes of ADU: Class 1 ADUs approved under Gov. Code §66323 (for example, a detached unit up to 800 sq ft with 4-foot side and rear setbacks), and Class 2 ADUs under §§66314–66322.
- Height (§17.21.060(B)): detached ADUs 16 feet; 18 feet within a half-mile walk of a major transit stop or high-quality transit corridor, plus 2 feet for roof pitch; attached ADUs 25 feet or the zone limit, whichever is lower, with a maximum of two stories.
- Class 2 size (§17.21.070(A)): 850 sq ft for a studio or one-bedroom; 1,000 sq ft for two or more bedrooms. An attached ADU is limited to 50% of the existing home's floor area, but never below 800 sq ft.
- Setbacks: 4 feet on the side and rear.
- Class 2 design (§17.21.070(H)–(K)): materials, colors and roof slope match the main home; windows and doors within 30 feet of a non-street property line use clerestory or obscure glass; evergreen screening or a 6-foot fence; detached Class 2 ADUs are one story. These standards don't block a §66323 unit.
- Rentals: no ADU or JADU may be rented for less than 30 days (§17.21.060(D)).
- Owner occupancy: the current code says ADUs are not subject to an owner-occupancy requirement; JADUs require owner occupancy unless the JADU has its own sanitation facilities (§17.21.060(G)). The city's web page still mentions owner occupancy, but the code text is newer.
Hermosa Beach review and the Coastal Zone
Under §17.21.040, the city decides completeness within 15 business days and approves or denies within 60 days, with no hearing. If a CDP is required, a complete CDP application is part of a complete ADU application, and because the city has no certified LCP it notifies the Coastal Commission (§17.21.040(C)(6)).
According to the city's Local Coastal Plan page, the Coastal Zone covers roughly 43% of the city, from the beach inland to Ardmore Avenue with some exceptions. CDPs are issued by the Coastal Commission's South Coast District after the city's approval in concept. Hermosa Beach does not list a pre-approved ADU plan program.
Side by side: local size and rental rules
| City | Local size limit | Minimum rental | Pre-approved plans |
|---|---|---|---|
| Torrance | Confirm with Planning (2025 amendments) | 30 days | Yes, four one-story plans |
| Redondo Beach | 850 sq ft (studio/1-bed), 1,000 sq ft (2+ bed) | 30 consecutive days | Yes, AB 1332 ADU Master Plan Program |
| Hermosa Beach | 850 sq ft (studio/1-bed), 1,000 sq ft (2+ bed), Class 2 | 30 days | None listed |
In every city, the state's 800 sq ft detached ADU option applies regardless of the local size limit.
Planning a South Bay ADU
- Check the parcel: its zone, and whether it is in the Coastal Zone.
- Pick the standard: a state-standard (800 sq ft) ADU or a local-standard ADU under the city's ordinance.
- Consider pre-approved plans in Torrance or Redondo Beach.
- Feasibility: setbacks, utilities, access and any coastal review.
- Plans, then plan check with the city.
If you are weighing a converted garage or a smaller unit inside the house, see junior ADU vs. ADU. For planning ranges, try the cost estimator. Adding a bedroom suite to the main house instead? Our South Bay master suite permit guide covers that path. The Los Angeles County service area page covers the rest of the county.
Nearby: Westside ADU rules for Culver City, Venice and West LA.
Frequently asked questions
Do I need a coastal permit for an ADU in Redondo Beach, Torrance or Hermosa Beach?+
If the lot is in the Coastal Zone, usually some coastal review is needed: a coastal development permit (CDP), a waiver or an exemption. Redondo Beach handles it under its certified Local Coastal Program; in Torrance and Hermosa Beach the California Coastal Commission issues it. State law requires a decision on an ADU coastal permit within 60 days, without a public hearing (Gov. Code §66329).
How big can an ADU be in Redondo Beach or Hermosa Beach?+
Under both cities' local standards, up to 850 sq ft for a studio or one-bedroom ADU, or 1,000 sq ft for two or more bedrooms. The state option for a detached ADU of up to 800 sq ft with 4-foot side and rear setbacks also applies.
Can I rent my South Bay ADU on Airbnb?+
Not for short stays. Torrance, Redondo Beach and Hermosa Beach all bar renting an ADU for less than 30 days.
Do I have to replace garage parking if I convert it to an ADU?+
No. When a garage, carport or covered parking structure is demolished or converted for an ADU, the city cannot require replacement parking (Gov. Code §66314(d)(11)).
Are there pre-approved ADU plans in the South Bay?+
Yes in Torrance, which offers four one-story pre-approved plans, and in Redondo Beach, through its AB 1332 ADU Master Plan Program. Hermosa Beach does not list a pre-approved plan program.
Will I pay impact fees on a South Bay ADU?+
Not on an ADU of 750 sq ft or less of interior livable space (Gov. Code §66311.5). Larger ADUs are charged proportionately to the main home, and other permit and plan-check fees still apply.
Planning an ADU in Torrance, Redondo Beach or Hermosa Beach?
Send us your address and what you want to build. We'll check the zone, whether the lot is in the Coastal Zone and which city standards apply, and lay out the permit path in order — no obligation.
Plan your project
Sources
Official references for the rules mentioned above. Local rules and site conditions vary; confirm with the agency that reviews your address.
- California Government Code § 66311.5 — ADU impact fees
- California Government Code § 66314 — ADU setbacks and parking
- California Government Code § 66315 — Owner occupancy
- California Government Code § 66317 — ADU permit review
- California Government Code § 66323 — ADUs that must be approved
- California Government Code § 66329 — ADUs in the Coastal Zone
- California HCD — ADU Handbook (March 2026)
- California Coastal Commission — SB 1077 ADU Guidance (July 1, 2026)
- California Coastal Commission — SB 1077
- City of Torrance — Planning Division
- City of Torrance — Building and Safety
- City of Torrance — Planning FAQ
- Torrance Municipal Code §§ 92.2.10–92.2.11 — ADUs and JADUs
- City of Torrance — Pre-Approved Accessory Dwelling Units
- City of Torrance — Online Permit Center Portal
- City of Torrance — Plan Check
- City of Redondo Beach — Accessory Dwelling Unit
- Redondo Beach Municipal Code § 10-2.1506 — ADUs
- Redondo Beach Municipal Code § 10-5.2208 — Coastal development permits
- City of Redondo Beach — AB 1332 ADU Master Plan Program
- City of Redondo Beach — ADU checklists and sample application
- City of Redondo Beach — iWorQ permit portal
- City of Hermosa Beach — ADU
- Hermosa Beach Municipal Code Chapter 17.21 — ADUs and JADUs
- City of Hermosa Beach — Local Coastal Plan