Skip to content
Permits & process · Published November 2026

Home Additions in Hidden Hills, CA: Permits and Approvals

An addition in Hidden Hills runs on two tracks: City permits and the Hidden Hills Community Association's architectural review. Here is who does what, the zoning basics, the fire-zone rules and how ADUs fit in.

By Eli Cohen·

Quick answer

Hidden Hills runs its own Building and Safety Department, which handles plan check, permits and inspections for additions. Most projects inside the gates also need approval from the Hidden Hills Community Association's Architectural Committee, a private body the City does not control. The southern and western parts of the city are in a Very High Fire Hazard Severity Zone.

Key takeaways

  • There are two tracks: the City issues building and grading permits, and the HHCA handles architectural review.
  • Per the City's Housing Element, projects that get Association approval are exempt from City Site Plan Review; otherwise Site Plan Review goes to the City Council at a public hearing.
  • Large setbacks apply. The Housing Element lists R-A-S lots at a 1-acre minimum, 30% maximum building coverage, and 50 ft front / 25 ft side / 50 ft rear setbacks. Confirm with staff.
  • ADUs are permitted in the residential zones, and state ADU law still applies.
Single-story home addition, shown as design inspiration
Design inspiration — not a HomeAdd project photo.

Hidden Hills is its own city, with its own City Hall and Building and Safety Department. Whether you are planning home additions, a room addition or a backyard ADU, the permit comes from the City, and you should expect to need approval from the Hidden Hills Community Association (HHCA) as well.

This is general planning information from HomeAdd, not legal advice for your property. City codes, handouts and Association standards change. Confirm current requirements with City staff and the HHCA before you design.

Who does what: City vs. HHCA

The City's City Hall or HHCA page splits the work. The City handles "Building & Grading Permits," building code enforcement, subdivisions, lot line adjustments and variances. The HHCA handles "Architectural Review and Standards," the gates, streets, trees and 3-rail fencing. In the City's words: "HHCA oversees gate access, all infrastructure within the gates, and architectural standards."

  • City Building and Safety "provides plan check, permit issuance, and inspection services for new construction, additions and remodels" (Building and Safety).
  • HHCA Architectural Committee: the City's 6th Cycle Housing Element says "nearly all projects within the Hidden Hills Association require approval of the Association's Architectural Committee, which is not under City control." Expect to need HHCA Architectural Committee approval.
  • Site Plan Review: per the Housing Element, projects that get Association approval are exempt from City Site Plan Review; Site Plan Review applications go to the City Council at a public hearing.

Zoning basics

The Housing Element (Table IV-2, citing the Hidden Hills Zoning Code) lists these standards. They are per the City's Housing Element — confirm with City staff.

Hidden Hills residential zoning standards per the City's Housing Element
ZoneMin. lotMax. coverageFront / side / rear
R-A-S / R-A-S-21 acre30%50 ft / 25 ft / 50 ft
R-120,000 sq ft30%35 ft / 5 ft / 15 ft

Per the City's Housing Element — confirm with City staff. The maximum building envelope height is 26 to 34 feet "depending on setback."

The City's residential plan checklist also notes a 50-foot rear-yard setback from the road easement and a ridge height certified by a licensed surveyor. For how setbacks shape an ADU, see ADU setback requirements in California.

Planning approvals that can apply

The City's planning permit application covers Site Plan Review, Minor Site Plan Review, Director's Review, Variance, Minor Accommodation, Conditional Use Permit and Tree Permit. Applications need a list of property owners within a 100-foot radius.

According to the City's Housing Element, discretionary processing typically takes about 90 days after an application is complete, and building plan check is generally one to two weeks. Those figures are the City's, not a HomeAdd timeline.

The permit process

  • Online portal: permits are filed through hiddenhills.cts.city. The City's Permit Center lists uploads that include structural sheets and calculations, Title 24 energy reports, soils/geotechnical reports and HOA approval documents. Inspections are requested in the portal.
  • Fire approval: the plan checklist lists Fire Prevention Bureau approval before permit issuance.
  • Grading and location forms: the City's downloadable forms include grading plan check correction lists, rough and final grading certifications and a Building Location Certification.
  • City Hall: 6165 Spring Valley Rd, (818) 888-9281.

For the broader permit sequence in Los Angeles County, see our home addition permit guide for Los Angeles.

Fire zone and defensible space

The City's Housing Element says "the southern and western portions of the city are within the Very High Fire Hazard Severity Zone." The LA County Fire Department runs the Defensible Space Inspection Program in Hidden Hills, with inspections beginning May 1.

Check your parcel on the state's Fire Hazard Severity Zone viewer; for parcels in a Local Responsibility Area, contact the local jurisdiction.

ADUs in Hidden Hills

ADUs are permitted in the R-A-S, R-A-S-2 and R-1 zones, according to the Housing Element.

  • Pre-approved detached ADU plans: the City's ADU page describes a program for detached ADUs of 250 to 800 sq ft, one story and up to 16 feet tall. HHCA Architectural Committee approval comes first, then a City building permit, and the City acts on detached ADUs within 30 days of a complete application. Check the City's ADU page for which plans are currently pre-approved.
  • Code update: in its Housing Element (Program 6b), the City has committed to update its ADU rules — confirm the current standards.

State ADU rules still apply

  • Side and rear setbacks of no more than 4 feet for a new ADU (Gov. Code §66314(d)(7)).
  • No owner-occupancy requirement for ADUs (§66315).
  • Ministerial approval for qualifying ADUs, including one detached ADU with 4-foot side and rear setbacks (§66323).

Calabasas is different

Neighboring Calabasas is a separate city with its own Building & Safety and Planning divisions, so its permit path is not the same as Hidden Hills'. If your property is in Calabasas, see home and room additions in Calabasas and ADUs and additions in Calabasas.

Planning your Hidden Hills addition

  1. Feasibility: confirm the zone, setbacks, coverage, height envelope and fire zone for the lot.
  2. HHCA review: take the design to the Architectural Committee.
  3. City approvals: any planning approval the project needs, then plan check and the building permit through the portal.

Read the home addition cost guide, or try the cost estimator for a planning range. The Los Angeles County service area page covers the nearby cities.

Frequently asked questions

Who issues building permits in Hidden Hills?+

The City of Hidden Hills' own Building and Safety Department, which handles plan check, permit issuance and inspections for additions.

Do I need HHCA approval for an addition?+

Expect to. The City's Housing Element says nearly all projects within the Hidden Hills Association require approval of the Association's Architectural Committee, which is not under City control.

What are the setbacks on a typical Hidden Hills lot?+

Per the City's Housing Element, R-A-S lots have a 50 ft front, 25 ft side and 50 ft rear setback, with 30% maximum building coverage on a 1-acre minimum lot. Confirm the standards for your parcel with City staff.

Is Hidden Hills in a high fire hazard zone?+

Partly. The City's Housing Element says the southern and western portions of the city are within the Very High Fire Hazard Severity Zone, and the LA County Fire Department inspects defensible space.

Can I build an ADU in Hidden Hills?+

Yes. ADUs are permitted in the R-A-S, R-A-S-2 and R-1 zones. The City has a pre-approved detached ADU plan program (250 to 800 sq ft, one story, up to 16 ft); HHCA Architectural Committee approval comes first, then a City building permit, and state ADU rules still apply.

Next step

Planning an addition in Hidden Hills?

Send us your address and what you want to add. We'll check the zone, setbacks and fire zone on the lot, which approvals apply, and lay out the steps in order — no obligation.

CallFree property check